Contents

                        Executive Summary                                                              

1                      Introduction                                                                           

1.1                   Background                                                                            

1.2                   Project Description                                                           

1.3                   Purpose of the Baseline Monitoring Report for Tung Chung East      

1.4                   Structure of the Baseline Monitoring Report for Tung Chung East

2                      Air Quality                                                                               

2.1                   Monitoring Requirement                                                   

2.2                   Monitoring Equipment                                                        

2.3                   Monitoring Locations                                                        

2.4                   Monitoring Parameters, Frequency and Duration  

2.5                   Monitoring Methodology                                                 

2.6                   Weather Data                                                                         

2.7                   Baseline Monitoring Results                                         

2.8                   Action and Limit Level                                                        

2.9                   Event and Action Plan                                                        

3                      Noise                                                                                           

3.1                   Monitoring Requirement                                                   

3.2                   Monitoring Equipment                                                        

3.3                   Monitoring Locations                                                        

3.4                   Monitoring Parameters, Frequency and Duration  

3.5                   Monitoring Methodology                                                 

3.6                   Maintenance and Calibration                                         

3.7                   Baseline Monitoring Results                                         

3.8                   Action and Limit Levels                                                      

3.9                   Event and Action Plan                                                        

4                      Water Quality                                                                        

4.1                   Monitoring Requirement                                                   

4.2                   Monitoring Locations                                                        

4.3                   Monitoring Parameters and Frequency                   

4.4                   Monitoring Methodology                                                 

4.5                   QA/QC Requirements                                                            

4.6                   Baseline Monitoring Results                                         

4.7                   Action and Limit Levels                                                      

4.8                   Event and Action Plan                                                        

5                      Landscape and Visual                                                         

5.1                   Monitoring Requirement                                                   

5.2                   Monitoring Methodology                                                 

5.3                   Monitoring Results                                                             

5.4                   Summary                                                                                    

6                      Soft Shore EcologY                                                            

6.1                   Monitoring Requirement                                                   

6.2                   Monitoring Locations                                                        

6.3                   Monitoring Methodology                                                 

6.4                   Baseline Monitoring Results                                         

6.5                   Event and Action Plan                                                        

7                      Conclusion                                                                              

 

ANNEXES

Annex A       Air Quality

Annex A1   Calibration Certificates for the Air Quality Monitoring Equipment

Annex A2   Wind Data at Chek Lap Kok Collected by the Hong Kong Observatory

Annex A3   1-Hour TSP Monitoring Results

Annex A4   Graphical Presentation of 1-Hour TSP Monitoring Results

Annex B       Noise

Annex B1   Calibration Certificates for the Noise Monitoring Equipment

Annex B2   Noise Monitoring Results

Annex B3  Graphical Presentation of Noise Monitoring Results

Annex C       Water Quality

Annex C1   Calibration Certificates for the Water Quality Monitoring Equipment

Annex C2   Baseline Water Quality Monitoring Schedule

Annex C3   Water Quality Monitoring Results

Annex C4   Graphical Presentation of Water Quality Monitoring Results

Annex D       Soft Shore Ecology

Annex D1   Raw Data for Qualitative Walk-through Survey

Annex D2  Raw Data for Quantitative Transect Survey

 

Executive Summary

The development of the Tung Chung New Town Extension (TCNTE), comprising Tung Chung East (TCE) and Tung Chung West (TCW), is a mega-scale and complex project aiming to provide land to meet the future housing, economic and social development needs of Hong Kong.  Due to the fact that the proposed works are geographically separated, the implementation of the mega-scale project is divided into two packages, namely TCE and TCW respectively.  ERM-Hong Kong, Limited (ERM) is commissioned to undertake the role of Environmental Team (ET) for the construction and operation of TCE Project (¡§the Project¡¨) in accordance with the requirements specified in the EP, Updated Environmental Monitoring and Audit (EM&A) Manual, EIA Report of the TCNTE project and other relevant statutory requirements.

In accordance with the Updated EM&A Manual of the TCNTE project, baseline monitoring was undertaken for the Project prior to commencement of the construction works for the following baseline monitoring components:

Ÿ   Air Quality;

Ÿ   Noise;

Ÿ   Water Quality;

Ÿ   Landscape and Visual; and

Ÿ   Soft Shore Ecology.

The baseline air quality monitoring was conducted at four (4) monitoring stations (DM-1, DM-2A, DM-3A and DM-4A) between 4 and 17 May 2018.  Overall, the baseline air quality monitoring results are considered representative to the ambient air quality conditions of the sensitive receivers in the vicinity of the Project.  The Action and Limit Levels for air quality (1-hour TSP levels) were established based on the baseline monitoring results.

 

Baseline noise monitoring was conducted at four (4) monitoring stations (NMS-CA-1A, NMS-CA-2A, NMS-CA-3 and NMS-CA-4) between 4 and 18 May 2018.  The major noise sources identified at the monitoring station are the noise from road traffic, aircraft, MTR, renovation at Ying Tung Estate and insect.  The baseline monitoring results are considered representative of the ambient noise level.

Baseline water quality monitoring was conducted at seven (7) monitoring stations (TCE-C1, TCE-C2, TCE-WQM1, TCE-WQM2a, TCE-WQM2b, TCE-WQM3A and TCE-WQM4) between 25 April and 21 May 2018.  No observable pollution source was recorded at the monitoring stations and the baseline monitoring results are thus considered representative of the ambient water quality levels.  Action and Limit Levels were established for DO, SS and Turbidity based on the baseline monitoring results.

 

Site conditions verification surveys for landscape and visual baseline were conducted on 15, 16, 17 and 19 May 2018 to revisit the identified Landscape Resources (LRs), Landscape Character Areas (LCAs) and Visual Sensitive Receivers (VSRs) in the approved EIA Report.  The survey results concluded that the landscape and visual baseline conditions within the Project site boundary is similar to those presented in the approved EIA Report.  There is no major change in the landscape and visual baseline conditions comparing to those during the EIA stage.  Additional landscape and visual mitigation measures other than those recommended in the approved EIA Report are thus not required.

Baseline soft shore ecological monitoring was conducted at four (4) monitoring stations situated in Tung Chung Bay and Tai Ho Wan on 30 April, 2-4 May, 15-16 May and 27 June 2018.  A total of 8,043 intertidal individuals and 37 individuals of horseshoe crabs were recorded during the surveys.  The baseline mudflat surface levels at the four (4) monitoring stations were also measured for the determination of sedimentation rate during the impact/post-construction monitoring.  Event and Action Plan is established for implementing appropriate actions and additional mitigation measures as necessary when comparing the data between baseline and impact/post-construction monitoring.

Upon agreement with EPD on this Baseline Monitoring Report for Tung Chung East, the Action and Limit Levels and the Event and Action Plan as proposed in this Report will be included in the next version of the Updated EM&A Manual.


1                                          Introduction

1.1                                   Background

The development of the Tung Chung New Town Extension (TCNTE), comprising Tung Chung East (TCE) and Tung Chung West (TCW), is a mega-scale and complex project aiming to provide land to meet the future housing, economic and social development needs of Hong Kong.  The Environmental Impact Assessment (EIA) Report for TCNTE (Register No. AEIAR-196/2016) ([1]) was approved on 8 April 2016 and the Environmental Permit (EP) EP-519/2016, covering the construction and operation of TCNTE, was granted on 9 August 2016.  The EIA Report and EP cover both TCE and TCW.

Due to the fact that the proposed works are geographically separated, the implementation of the mega-scale project is divided into two packages, namely TCE and TCW, respectively.  ERM-Hong Kong, Limited (ERM) is commissioned to undertake the role of Environmental Team (ET) for the construction and operation of TCE Project (¡§the Project¡¨) in accordance with the requirements specified in the EP, Updated Environmental Monitoring and Audit (EM&A) Manual ([2]), EIA Report of the TCNTE project ([3]) and other relevant statutory requirements.

1.2                                   Project Description

The TCE Project (¡§the Project¡¨) comprises the following elements:

1.       Reclamation of the seabed by a non-dredged method at TCE to form a total of about 130 hectares of land;

2.       Construction of about 4.9 kilometres of seawalls, with an eco-shoreline, three drainage box culvert outfalls, three circulation drains and a seawater intake at TCE;

3.       Construction of a 470-metre (m) long multi-cell drainage box culvert at TCE;

4.       Provision of infrastructure for Tung Chung Area 58, including construction of a single two-lane road with a footpath of about 270 m in length and the associated utility works;

5.       Construction of roads, footbridges, drainage, sewerage, waterworks, sewage and salt water pumping stations, fresh water and salt water service reservoirs, and flood protection measures;

6.       Provision of new cycle tracks connecting to the existing cycle track network;

7.       Landscaping, reprovisioning and ancillary works; and

8.       Implementation of environmental mitigation measures and environmental monitoring and audit works.

The location of the Project, including the associated infrastructure works, is shown in Figure 1.1.

1.3                                   Purpose of the Baseline Monitoring Report for Tung Chung East

The purpose of this Baseline Monitoring Report for Tung Chung East is to present the baseline levels of air quality, noise, water quality and marine ecology (particularly intertidal habitats in Tung Chung Bay and Tai Ho Wan) at the designated monitoring locations around the Project area prior to the commencement of construction works of the Project.  In addition, landscape and visual baseline monitoring were undertaken to verify the site conditions with reference to the approved EIA Report.  Such baseline conditions will be used as the basis for assessing environmental impacts, if any, and compliance monitoring during the construction works of the Project. 

Under the requirement of Condition 3.4 of the EP, the Baseline Monitoring Report shall be prepared and submitted to the Director of the Environmental Protection (DEP) at least two weeks before the commencement of any construction works of the Project.

1.4                                   Structure of the Baseline Monitoring Report for Tung Chung East

Following this introductory section, the remainder of the Baseline Monitoring Report for Tung Chung East is structured as follows:

Section 2    Air Quality ¡V presents the methodology and findings of the baseline air quality monitoring.

Section 3    Noise ¡V presents the methodology and findings of the baseline noise monitoring.

Section 4    Water Quality ¡V presents the methodology and findings of the baseline water quality monitoring.

Section 5    Landscape and Visual ¡V presents the methodology and findings of the baseline landscape and visual monitoring.

Section 6    Soft Shore Ecology ¡V presents the methodology and findings of the baseline soft shore ecological monitoring.

Section 7    Conclusion

2                                          Air Quality

2.1                                   Monitoring Requirement

According to the Updated EM&A Manual ([4]) of the Project, baseline air quality monitoring shall be carried out at the designated monitoring locations for at least 14 consecutive days prior to the commissioning of major construction works of the Project to obtain 1-hour Total Suspended Particulate (TSP) samples.  The selected baseline monitoring stations should reflect baseline conditions at the impact stations.  One-hour sampling should be done at least 3 times per day while the highest dust impact is expected.  Further details of the baseline air quality monitoring are presented in the following sections.

2.2                                   Monitoring Equipment

Portable direct reading dust meters were used to measure 1-hour TSP levels in undertaking the air quality monitoring for the Project.  The proposed use of portable direct reading dust meters was submitted to the Independent Environmental Checker (IEC) and obtained agreement from the IEC as stated in Section 5.5 of the Updated EM&A Manual.  With the use of direct reading dust meter, it can allow prompt and direct results for the EM&A reporting and the implementation of the event and action plan.  The portable direct reading dust meter would be calibrated every year against HVS to check the validity and accuracy of the results measured by direct reading method.

Table 2.1 summarizes the equipment used in the baseline air quality monitoring programme.  Copies of the calibration certificates for the equipment are presented in Annex A1, which showed that the portable direct reading dust meter is capable of providing comparable results with that provided by a High Volume Sampler (HVS).

Table 2.1        Air Quality Monitoring Equipment

Equipment

Monitoring Station

Model

1-hour TSP Dust Meter

DM-1

SIBATA LD-5R (S/N: 620402)

DM-2A

SIDEPAK AM510 (S/N: 10406054)

DM-3A

SIDEPAK AM510 (S/N: 11009015)

DM-4A

SIBATA LD-5R (S/N: 781282)

2.3                                   Monitoring Locations

Baseline air quality monitoring for the Project was conducted at four (4) monitoring stations around the Project area (ie DM-1, DM-2A, DM-3A and DM-4A).  Locations of the four monitoring stations are shown in Figure 2.1.

2.4                                   Monitoring Parameters, Frequency and Duration

Table 2.2 summarizes the monitoring parameters, monitoring period and frequency of baseline air quality monitoring.

Table 2.2        Frequency and Parameters of Baseline Air Quality Monitoring

Monitoring Station

Location

Parameter

Period

Frequency

DM-1

Tung Chung Area 56 ¡V Planned Public Rental Housing Development

1-hour TSP

0700-1900 for 14 consecutive days

3 times/ day

DM-2A (1)

Planned School in Tung Chung East

DM-3A (1)

Residential premise near Tung Chung East

DM-4A (1)

Pak Mong Pier

Remark: (1) Alternative Monitoring Station proposed in the Updated EM&A Manual

2.5                                   Monitoring Methodology

The 1-hour TSP levels were measured by the dust meter in accordance with procedures specified in the Manufacturer¡¦s Instruction Manual.  The general procedures are described as follows:

Ÿ   Pull up the air sampling inlet cover; and

Ÿ   Set the timer and make a measurement.

2.6                                   Weather Data

Wind data at Chek Lap Kok collected from the Hong Kong Observatory (HKO) were used for the air quality monitoring and they are shown in Annex A2.  It is considered that wind data obtained at the existing Chek Lap Kok Wind Station are representative of the Project area and could be used for undertaking the baseline and construction phase air quality monitoring programme for the Project.

The proposed use of the existing wind data from Chek Lap Kok Wind Station collected from HKO for wind data collection instead of setting up wind monitoring equipment near the monitoring stations was submitted and agreed by IEC, and Engineer¡¦s Representative (ER)¡¦s approval was also obtained in accordance with the requirements as stated in Section 5.5 of the Updated EM&A Manual.

2.7                                   Baseline Monitoring Results

The baseline air quality monitoring was conducted at four (4) monitoring locations (DM-1, DM-2A, DM-3A and DM-4A) between 4 and 17 May 2018 and the results are summarized in Table 2.3.  The detailed 1-hour TSP monitoring results are presented in Annex A3.  Graphical presentations of the 1-hour TSP results at each monitoring location are shown in Annex A4.  The weather was generally sunny and cloudy during the baseline monitoring period.  Road traffic dust is identified as the influencing factors which may affect the results of baseline monitoring.

Table 2.3        Summary of Baseline 1-hour TSP Monitoring Results

Monitoring Station

Average 1-hr TSP Concentration (µg/m3)
(Range)

DM-1 ¡V Tung Chung Area 56 ¡V Planned Public Rental Housing Development

49.7
(25.0-76.0)

 

DM-2A ¡V Planned School in Tung Chung East

42.4
(24.0-75.0)

 

DM-3A ¡V Residential premise near Tung Chung East

40.9
(24.0-63.0)

 

DM-4A ¡V Pak Mong Pier

45.9
(25.0-74.0)

 

 

Overall Average

44.7

2.8                                   Action and Limit Level

Guidelines for establishing the Action and Limit Levels for air quality monitoring during the construction of the Project are presented in Table 2.4.

Table 2.4        Guidelines for Establishing Action and Limit Levels for Air Quality

Parameters

Action Level

Limit Level

1-hour TSP Level in £gg/m3

For baseline level £ 384 £gg/m3,

Action level = (baseline level * 1.3 + Limit level)/2;

For baseline level > 384 £gg/m3,

Action level = Limit level

500 £gg/m3

Given the 1-hour TSP levels recorded at the four monitoring stations (DM-1, DM-2A, DM-3A and DM-4A) are similar (ranged from 40.9 - 49.7 µg/m3) during the baseline monitoring, it is considered appropriate to set up one Action Level for the Project instead of Action Levels for each monitoring station.  The Action and Limit Levels of 1-hr TSP levels for air quality impact monitoring are determined and presented in Table 2.5.

Table 2.5        Action and Limit Levels for 1-hour TSP

Location

Action Level, µg/m3

Limit Level, µg/m3

Monitoring stations for Tung Chung East (i.e. DM-1, DM-2, DM-3, DM-4, or other alternative monitoring stations proposed by the ET)

279

500

2.9                                   Event and Action Plan

Should non-compliance of the air quality criteria occur, actions in accordance with the Action Plan in Table 2.6 shall be carried out.


Table 2.6        Event and Action Plan for Air Quality

Event

Action

ET

IEC

ER

Contractor

Action level exceedance for one sample

1. Identify source, investigate the causes of exceedance and propose remedial measures;

2. Inform IEC and ER;

3. Repeat measurement to confirm finding;

4. Increase monitoring frequency to daily.

 

1. Check monitoring data submitted by ET;

2. Check Contractor¡¦s working method.

1. Notify Contractor.

1. Rectify any unacceptable practice;

2. Amend working methods if appropriate.

Action level exceedance for two or more consecutive samples

1. Identify source;

2. Inform IEC and ER;

3. Advise the ER on the effectiveness of the proposed remedial measures;

4. Repeat measurements to confirm findings;

5. Increase monitoring frequency to daily;

6. Discuss with IEC and Contractor on remedial actions required;

7. If exceedance continues, arrange meeting with IEC and ER;

8. If exceedance stops, cease additional monitoring.

1. Check monitoring data submitted by ET;

2. Check Contractor¡¦s working method;

3. Discuss with ET and Contractor on possible remedial measures;

4. Advise the ET on the effectiveness of the proposed remedial measures;

5. Supervise Implementation of remedial measures.

1. Confirm receipt of notification of failure in writing;

2. Notify Contractor;

3. Ensure remedial measures properly implemented.

 

1. Submit proposals for remedial to ER within 3 working days of notification;

2. Implement the agreed proposals;

3. Amend proposal if appropriate.

Limit level exceedance for one sample

1. Identify source, investigate the causes of exceedance and propose remedial measures;

2. Inform ER, Contractor and EPD;

3. Repeat measurement to confirm finding;

4. Increase monitoring frequency to daily;

5. Assess effectiveness of Contractor¡¦s remedial actions and keep IEC, EPD and ER informed of the results.

1. Check monitoring data submitted by ET;

2. Check Contractor¡¦s working method;

3. Discuss with ET and Contractor on possible remedial measures;

4. Advise the ER on the effectiveness of the proposed remedial measures;

5. Supervise implementation of remedial measures.

 

1. Confirm receipt of notification of failure in writing;

2. Notify Contractor;

3. Ensure remedial measures properly implemented.

1. Take immediate action to avoid further exceedance;

2. Submit proposals for remedial actions to IEC within 3 working days of notification;

3. Implement the agreed proposals;

4. Amend proposal if appropriate.

Limit level exceedance for two or more consecutive samples

1. Notify IEC, ER, Contractor and EPD;

2. Identify source;

3. Repeat measurement to confirm findings;

4. Increase monitoring frequency to daily;

5. Carry out analysis of Contractor¡¦s working procedures to determine possible mitigation to be implemented;

6. Arrange meeting with IEC and ER to discuss the remedial actions to be taken;

7. Assess effectiveness of Contractor¡¦s remedial actions and keep IEC, EPD and ER informed of the results;

8. If exceedance stops, cease additional monitoring.

1. Discuss amongst ER, ET, and Contractor on the potential remedial actions;

2. Review Contractor¡¦s remedial actions whenever necessary to assure their effectiveness and advise the ER accordingly;

3. Supervise the implementation of remedial measures.

1. Confirm receipt of notification of failure in writing;

2. Notify Contractor;

3. In consultation with the IEC, agree with the Contractor on the remedial measures to be implemented;

4. Ensure remedial measures properly implemented;

5. If exceedance continues, consider what portion of the work is responsible and instruct the Contractor to stop that portion of work until the exceedance is abated.

1. Take immediate action to avoid further exceedance;

2. Submit proposals for remedial actions to IEC within 3 working days of notification;

3. Implement the agreed proposals;

4. Resubmit proposals if problem still not under control;

5. Stop the relevant portion of works as determined by the ER until the exceedance is abated.

 

 


3                                          Noise

3.1                                   Monitoring Requirement

According to the Updated EM&A Manual ([5]) of the Project, baseline noise monitoring shall be carried out at the monitoring locations for a period of at least two weeks in a sample period interval of 5 minutes or 30 minutes between 0700 and 1900, and 5 minutes between 1900 and 0700.  The noise levels shall be measured in terms of A-weighted levels Leq, L10 and L90.  Details of the baseline noise monitoring are presented in the following sections.

3.2                                   Monitoring Equipment

Integrating Sound Level Meter was used for noise monitoring.  The meter is a Type 1 sound level meter capable of giving a continuous readout of the noise level readings including equivalent continuous sound pressure level (Leq) and percentile sound pressure level (Lx).  The meter used also complied with International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications.  The noise monitoring equipment used is presented in Table 3.1 and copies of the calibration certificates for the sound level meter and calibrator are presented in Annex B1.

Table 3.1        Noise Monitoring Equipment

Equipment

Monitoring Station

Model

Sound Level Meter

NMS-CA-1A

Rion NL-31 (S/N: 00603867)

NMS-CA-2A

Rion NL-52 (S/N: 00331805)

NMS-CA-3

Rion NL-52 (S/N: 00131627)

NMS-CA-4

Rion NL-52 (S/N: 01010406)

Calibrator

All Station

LARSON DAVIS CAL200 (S/N: 11334)

3.3                                   Monitoring Locations

Baseline noise monitoring for the Project was conducted at four (4) monitoring stations around the Project area (ie NMS-CA-1A, NMS-CA-2A, NMS-CA-3 and NMS-CA-4).  Locations of the four monitoring stations are shown in Figure 3.1. 

3.4                                   Monitoring Parameters, Frequency and Duration

In accordance with the Updated EM&A Manual, baseline noise for the A-weighted levels Leq, L10 and L90 was recorded.  The frequency and parameters of noise measurement are presented in Table 3.2.

Table 3.2        Frequency and Parameters of Noise Monitoring

Monitoring Station

Location for Measurement

Time Period

Duration, min

Parameter

NMS-CA-1A

Residential premise near Tung Chung East

 

Daytime on normal weekdays (0700-1900 hrs) for 2 weeks


Evening and Night time on all days (1900-0700 hrs) and daytime during public holidays (including Sundays) (0700-1900 hrs) for 2 weeks

 

30 min


5min

Leq, L10 & L90

NMS-CA-2A

Pak Mong Pier

 

NMS-CA-3

School in the reclamation area next to Tung Chung East

 

NMS-CA-4

Residential premise in the reclamation area next to Tung Chung East

Remark: (1) Alternative Monitoring Station proposed in the Updated EM&A Manual

3.5                                   Monitoring Methodology

The monitoring procedures are as follows:

Ÿ   The sound level meter was set at least 1.2 m above the ground for free-field measurements at monitoring stations NMS-CA-1A, NMS-CA-2A, NMS-CA-3 and NMS-CA-4.  A correction of +3 dB(A) has been made for the free field measurements.

Ÿ   The battery condition was checked to ensure good functioning of the meter.

Ÿ   Parameters such as frequency weighting, time weighting and measurement time were set as follows:

-                                         frequency weighting:     A

-                                         time weighting:    Fast

-                                         measurement time:       5 minutes (Leq (30-min) would be determined for daytime noise by calculating the logarithmic average of six Leq (5min) data)

Ÿ   Prior to and after noise measurement, the meter was calibrated using the calibrator for 94.0 dB at 1,000 Hz.  If the difference in the calibration level before and after measurement was more than 1.0 dB, the measurement was considered invalid and repeat of noise measurement was required after re-calibration or repair of the equipment.

Ÿ   Noise monitoring was carried out continuously for 24 hours during the 14 days baseline monitoring period.  Monitoring data were recorded and stored automatically within the sound level meter system.  At the end of the monitoring period, noise levels in term of Leq, L90 and L10 were recorded.  In addition, site conditions and noise sources were recorded when the equipment were checked and inspected every 2-3 days.

Ÿ   All the monitoring data stored in the sound level meter system were downloaded through the computer software, and all these data were checked and reviewed on computer.

3.6                                   Maintenance and Calibration

Maintenance and calibration procedures were as follows:

Ÿ   The microphone head of the sound level meter and calibrator were cleaned with a soft cloth at quarterly intervals;

Ÿ   The sound level meter and calibrator were checked and calibrated at yearly intervals; and

Ÿ   Immediately prior to and following each noise measurement, the accuracy of the sound level meter should be checked using an acoustic calibrator generating known sound pressure level at known frequency.  Measurements may be accepted as valid only if the calibration levels from before and after the noise measurement agree to within 1.0 dB.

3.7                                   Baseline Monitoring Results

Baseline noise monitoring was conducted at four (4) monitoring stations (NMS-CA-1A, NMS-CA-2A, NMS-CA-3 and NMS-CA-4) between 4 and 18 May 2018.

The baseline noise monitoring results are summarized in Tables 3.3 to 3.5.  All baseline noise monitoring results are presented in Annex B2.  Graphical presentations of the data are provided in Annex B3.  The weather was generally sunny and cloudy during the baseline monitoring period.  Road traffic, aircraft, train, renovation at Ying Tung Estate and insect noises were noted as the possible influencing factors which may affect the baseline monitoring results.

Table 3.3        Summary of Noise Monitoring Results during Normal Working Hours (0700-1900 hours; Normal Weekdays)

Normal Working Hours (0700-1900 hours; Normal Weekdays)

Measured Noise Level Leq (30 min), dB(A)

Average

Min

Max

NMS-CA-1A

63.2

56.4

68.4

NMS-CA-2A

64.6

59.9

70.9

NMS-CA-3

67.4

60.2

83.7

NMS-CA-4

67.9

53.2

83.7

 

                       

Table 3.4        Summary of Noise Monitoring Results during Evening on Normal Weekdays (1900-2300 hours) and Holidays (0700-2300 hours)

Evening on Normal Weekdays (1900-2300 hours) and Holidays (0700-2300 hours)

Measured Noise Level Leq (5 min), dB(A)

Average

Min

Max

NMS-CA-1A

62.3

50.4

72.4

NMS-CA-2A

63.8

54.1

71.6

NMS-CA-3

65.0

52.3

76.8

NMS-CA-4

61.3

50.9

76.2

 

Table 3.5        Summary of Noise Monitoring Results during Night-time (2300-0700 hours)

Night-time (2300-0700 hours)

Measured Noise Level Leq (5 min), dB(A)

Average

Min

Max

NMS-CA-1A

62.1

44.1

83.2

NMS-CA-2A

62.4

48.5

79.7

NMS-CA-3

63.6

45.8

82.1

NMS-CA-4

63.2

45.1

84.3

3.8                                   Action and Limit Levels

The Action and Limit Levels were established in accordance with the Updated EM&A Manual.  The baseline noise level should be referenced during the compliance check during the impact noise monitoring period.  Table 3.6 presents the Action and Limit Levels for construction noise of the Project.

 

Table 3.6        Action and Limit Levels for Construction Noise

Time Period

Action Level

Limit Level

0700 - 1900 hours on normal weekdays

When one documented complaint is received

75 dB(A) *

Notes:      

If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to be followed.

*  Reduce to 70 dB(A) for schools and 65 dB(A) during school examination periods.

3.9                                   Event and Action Plan

Should non-compliance of the noise criteria occur, actions in accordance with the Action Plan in Table 3.7 shall be carried out.


Table 3.7        Event and Action Plan for Construction Noise

Event

Action

ET

IEC

ER

Contractor

Action Level Exceedance

1. Notify IEC, ER and Contractor;

2. Carry out investigation;

3. Report the results of investigation to the IEC, ER and Contractor;

4. Discuss with the Contractor and formulate remedial measures;

5. Increase monitoring frequency to check mitigation effectiveness.

1. Review the analysed results submitted by the ET;

2. Review the proposed remedial measures by the Contractor and advise the ER accordingly;

3. Supervise the implementation of remedial measures.

1. Confirm receipt of notification of failure in writing;

2. Notify Contractor;

3. Require Contractor to propose remedial measures for the analysed noise problem;

4. Ensure remedial measures are properly implemented

1. Submit noise mitigation proposals to IEC and ER;

2. Implement noise mitigation proposals.

Limit Level Exceedance

1. Identify source;

2. Inform IEC, ER, EPD and Contractor;

3. Repeat measurements to confirm findings;

4. Increase monitoring frequency;

5. Carry out analysis of Contractor¡¦s working procedures to determine possible mitigation to be implemented;

6. Inform IEC, ER and EPD the causes and actions taken for the exceedances;

7. Assess effectiveness of Contractor¡¦s remedial actions and keep IEC, EPD and ER informed of the results;

8. If exceedance stops, cease additional monitoring.

1. Discuss amongst ER, ET, and Contractor on the potential remedial actions;

2. Review Contractors remedial actions whenever necessary to assure their effectiveness and advise the ER accordingly;

3. Supervise the implementation of remedial measures.

1. Confirm receipt of notification of failure in writing;

2. Notify Contractor;

3. Require Contractor to propose remedial measures for the analysed noise problem;

4. Ensure remedial measures properly implemented;

5. If exceedance continues, consider what portion of the work is responsible and instruct the Contractor to stop that portion of work until the exceedance is abated.

1. Take immediate action to avoid further exceedance;

2. Submit proposals for remedial actions to IEC  within 3 working days of notification;

3. Implement the agreed proposals;

4. Resubmit proposals if problem still not under control;

5. Stop the relevant portion of works as determined by the ER until the exceedance is abated.

 


4                                          Water Quality

4.1                                   Monitoring Requirement

According to the Updated EM&A Manual ([6]) of the Project, baseline water quality monitoring shall be carried out three (3) times per week for at least 4 weeks prior to the commencement of construction works of the Project.  The measurement should be taken at all designated monitoring stations for the Project, including control stations, at mid-flood and mid-ebb tides.  Further details of the baseline water quality monitoring under this Project are presented in the following sections.

4.2                                   Monitoring Locations

Baseline water quality monitoring was conducted at seven (7) monitoring stations under the Project.  Coordinates of the monitoring stations are summarized in Table 4.1.  Locations of the monitoring stations are shown in Figure 4.1. 

Table 4.1        Marine Water Quality Monitoring Locations

Monitoring Stations

Description

Coordinates

Easting

Northing

TCE-WQM1

Near Airport Channel

811838

817341

TCE-WQM2a

Marine Park 1

814439

819879

TCE-WQM2b

Marine Park 2

814439

821905

TCE-WQM3A

Outlet of Tai Ho Wan

814705

817859

TCE-WQM4

HKBCF

813344

818849

TCE-C1

Control Station - Outside Airport Channel

804247

815620

TCE-C2

Control Station - Sunny Bay

819460

821473

4.3                                   Monitoring Parameters and Frequency

Table 4.2 summarizes the monitoring parameters, monitoring period and frequencies of the water quality monitoring.


 

Table 4.2        Water Quality Monitoring Parameters and Frequency

Monitoring Stations

Parameters (Unit)

Depth

Frequency and Replication

TCE-WQM1

TCE-WQM2a

TCE-WQM2b

TCE-WQM3A (1)

TCE-WQM4

TCE-C1

TCE-C2

Ÿ Dissolved Oxygen (DO) (mg/L and % saturation)

Ÿ Temperature (¢XC)

Ÿ Turbidity (NTU)

Ÿ Salinity (ppt)

Ÿ pH

Ÿ Water depth (m)

Ÿ Suspended Solid (SS) (mg/L)

3 water depths: 1 m

below sea surface,

mid-depth and 1 m

above seabed.

Baseline monitoring:
3 days per week, at mid-flood and

mid-ebb tides, for 4 weeks prior to the commencement of construction work.

 

Two (2) replicate in-situ measurements and water samples.

 

 

If the water depth is

less than 3 m, mid-depth

sampling only.

 

If water depth less

than 6 m, mid-depth

may be omitted.

Remark: (1) Alternative Monitoring Station proposed in the Updated EM&A Manual

 

In addition to the parameters presented in Table 4.2, other relevant data shall also be recorded, including monitoring location / position, time, water depth, tidal stages, weather conditions and any special phenomena or work underway at the construction site.

4.4                                   Monitoring Methodology

4.4.1                           Instrumentation


Table 4.3 summarizes the equipment used in the baseline water quality monitoring works.  All the monitoring equipment complied with the requirements set out in the Updated EM&A Manual.  Copies of the calibration certificates are attached in Annex C1.

Table 4.3        Water Quality Monitoring Equipment

Equipment

Model

Water Sampler

Kahlsico Water Samplers

Multi-parameter Water Quality System (measurement of DO, Temperature, Turbidity, Salinity and pH) (Note 1)

YSI ProDSS (S/N: 15M100005; S/N: 16H104233; S/N: 16H104234; S/N: 17E100747; S/N: 17H105557)

YSI 6920 v2 (S/N: 0001C6A7; S/N: 000109DF)

Note 1: Two of the multi-parameter water quality systems were used at each monitoring station during each survey day.

4.4.2                           Operating/Analytical Procedures

At each sampling depth, two consecutive measurements of DO level, DO Saturation, Temperature, Turbidity, Salinity and pH were taken using two independent multi-parameter water quality systems.  Where the difference in the value between the first and second readings of each set was more than 25% of the value of the first reading, the reading was discarded and further readings were taken.  Two samples were collected for laboratory analysis of SS content.  Following collection, water samples for laboratory analysis were stored in high density polythene bottles (1L) with no preservatives added, packed in ice (cooled to 4¢XC without being frozen) and kept in dark during both on-site temporary storage and shipment to the testing laboratory.  The samples were delivered to the laboratory as soon as possible and the laboratory determination works started within 24 hours after collection of the water samples.  Sufficient volume of samples was collected to achieve the reporting limit.

4.4.3                           Laboratory Analytical Methods

The testing of SS for all stations was conducted by ALS Technichem (HK) Pty Ltd. (HOKLAS Registration No. 066).  Comprehensive quality assurance and control procedures were in place in order to ensure quality and consistency in results.  The testing method and reporting limit are provided in Table 4.4.

Table 4.4        Methods for Laboratory Analysis for Water Samples

Parameter

Analytical Method

Reporting Limit

Suspended Solids (SS)

APHA 17e 2540D

0.5 mg/L

4.5                                      QA/QC Requirements

4.5.1                           Calibration of In-situ Instruments

 

All in situ monitoring instruments were checked, calibrated and certified by a laboratory accredited under HOKLAS or other international accreditation scheme before use, and subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality monitoring programme.  Responses of sensors and electrodes were checked with certified standard solutions before each use.  Wet bulb calibration for a DO meter was carried out before measurement at each monitoring event.

 

For the on-site calibration of field equipment (Multi-parameter Water Quality System), the BS 1427:2009, "Guide to on-site test methods for the analysis of waters" was observed.

 

Sufficient stocks of spare parts were maintained for replacements when necessary.  Backup monitoring equipment was also being made available so that monitoring can proceed uninterrupted even when some equipment was under maintenance, calibration, etc.

4.5.2                           Decontamination Procedures

 

Water sampling equipment used during the course of the monitoring programme was decontaminated by manual washing and rinsed clean seawater/distilled water after each sampling event.  All disposable equipment was discarded after sampling.

4.5.3                           Sampling Management and Supervision

 

All sampling bottles were labeled with the sample ID (including the indication of sampling station and tidal stage e.g. TCE-C1_ME_S_R1), laboratory number and sampling date.  Water samples were dispatched to the testing laboratory for analysis as soon as possible after the sampling.  All samples were stored in a cool box and kept at less than 4¢XC but without frozen.  All water samples were handled under chain of custody protocols and relinquished to the laboratory representatives at locations specified by the laboratory.  The laboratory determination works started within 24 hours after collection of water samples.

4.5.4                           Quality Control Measures for Sample Testing

 

The samples testing were performed by ALS Technichem (HK) Pty Ltd.  The following quality control programme was performed by the laboratory for every batch of 20 samples:

 

Ÿ   One method blank; and

Ÿ   One set of quality control (QC) samples (including method QC and sample duplicate).

4.6                                   Baseline Monitoring Results

Baseline water quality monitoring was conducted at seven (7) monitoring stations (TCE-C1, TCE-C2, TCE-WQM1, TCE-WQM2a, TCE-WQM2b, TCE-WQM3A and TCE-WQM4) between 25 April and 21 May 2018.  The detailed monitoring schedule is shown in Annex C2.  The monitoring results at each monitoring station are shown in Annex C3.  Graphical presentation of water quality (DO, Turbidity and SS) at the monitoring stations is given in Annex C4.  

During the baseline monitoring period, no marine construction works were observed in the vicinity of all monitoring stations.  The baseline monitoring results are thus considered representative of the ambient water quality of the Project area during the season.

4.7                                   Action and Limit Levels

The Action and Limit Levels for DO, Turbidity and SS are determined in accordance with requirements set out in the Updated EM&A Manual which are summarized in Table 4.5.

Table 4.5        Action and Limit Levels for Water Quality

Parameters

Action Level

Limit Level

DO in mg/L

(Surface, Middle & Bottom)

Surface and Middle

5 percentile of baseline data [1]

 

Bottom

5 percentile of baseline data

Surface and Middle

4 mg/L or 1 percentile of baseline data [1]

 

Bottom

2 mg/L or 1 percentile of baseline data

 

SS in mg/L (Depth-averaged)

95 percentile of baseline data or 120% of upstream control station at the same tide of the same day, whichever is higher. [2]

 

99 percentile of baseline data or 130% of upstream control station at the same tide of the same day, whichever is higher. [2]

Turbidity in NTU  (Depth-averaged)

95 percentile of baseline data or 120% of upstream control station at the same tide of the same day, whichever is higher. [2]

99 percentile of baseline data or 130% of upstream control station at the same tide of the same day, whichever is higher. [2]

Notes:

(1) For DO, non-compliance occurs when monitoring results is lower than the limits.

(2) For SS and Turbidity, non-compliance occurs when monitoring results is larger than the limits

The calculated Action and Limit levels are shown in Table 4.6.

Table 4.6        Calculated Action and Limit Levels for Water Quality

Parameters

Action Level

Limit Level

DO in mg/L

(Surface, Middle & Bottom)

Surface and Middle

5.9 mg/L [1]

 

Bottom

5.6 mg/L

Surface and Middle

4 mg/L [1]

 

Bottom

2 mg/L

 

SS in mg/L (Depth-averaged)

13.5 mg/L
or
120% of upstream control station at the same tide of the same day,
whichever is higher. [2]

 

23.5 mg/L
or
130% of upstream control station at the same tide of the same day,
whichever is higher. [2]

Turbidity in NTU (Depth-averaged)

17.1 NTU
or
120% of upstream control station at the same tide of the same day,
whichever is higher. [2]

23.5 NTU
or
130% of upstream control station at the same tide of the same day,
whichever is higher. [2]

Notes:

(1) For DO, non-compliance occurs when monitoring results is lower than the limits.

(2) For SS and Turbidity, non-compliance occurs when monitoring results is larger than the limits

4.8                                   Event and Action Plan

Should non-compliance of the criteria occur, action in accordance with the Event and Action Plan in the Table 4.7 below shall be carried out.


Table 4.7        Event and Action Plan for Water Quality

Event

Action

ET

IEC

ER

Contractor

Action level exceedance for one sampling day

1. Inform IEC, Contractor and ER;

2. Check monitoring data, all plant, equipment and Contractor¡¦s working methods; and

3. Discuss remedial measures with IEC and Contractor and ER.

1. Discuss with ET, ER and Contractor on the implemented mitigation measures;

2. Review proposals on remedial measures submitted by Contractor and advise the ER accordingly; and

3. Review and advise the ET and ER on the effectiveness of the implemented mitigation measures.

1. Discuss with IEC, ET and Contractor on the implemented mitigation measures;

2. Make agreement on the remedial measures to be implemented;

3. Supervise the implementation of agreed remedial measures.

1. Identify source(s) of impact;

2. Inform the ER and confirm notification of the non-compliance in writing;

3. Rectify unacceptable practice;

4.Check all plant and equipment;

5. Consider changes of working methods;

6. Discuss with ER, ET and IEC and purpose remedial measures to IEC and ER; and

7. Implement the agreed mitigation measures.

Action level exceedance for more than one consecutive sampling days

1. Repeat in-situ measurement on next day of exceedance to confirm findings;

2. Inform IEC, contractor and ER;

3. Check monitoring data, all plant, equipment and Contractor¡¦s working methods;

4. Discuss remedial measures with IEC, contractor and ER

5. Ensure remedial measures are implemented

1. Discuss with ET, Contractor and ER on the implemented mitigation measures;

2. Review the proposed remedial measures submitted by Contractor and advise the ER accordingly; and

3. Review and advise the ET and ER on the effectiveness of the implemented mitigation measures.

1. Discuss with ET, IEC and Contractor on the proposed mitigation measures;

2. Make agreement on the remedial measures to be implemented ; and

3. Discuss with ET, IEC and Contractor on the effectiveness of the implemented remedial measures.

1. Identify source(s) of impact;

2. Inform the ER and confirm notification of the non-compliance in writing;

3. Rectify unacceptable practice;

4. Check all plant and equipment and consider changes of working methods;

5. Discuss with ET, IEC and ER and submit proposal of remedial measures to ER and IEC within 3 working days of notification; and

6. Implement the agreed mitigation measures.

Limit level exceedance for one sampling day

1. Repeat measurement on next day of exceedance to confirm findings;

2. Inform IEC, contractor and ER;

3. Rectify unacceptable practice;

4. Check monitoring data, all plant, equipment and Contractor¡¦s working methods;

5. Consider changes of working methods;

6. Discuss mitigation measures with IEC, ER and Contractor; and

7. Ensure the agreed remedial measures are implemented

1. Discuss with ET, Contractor and ER on the implemented mitigation measures;

2. Review the proposed remedial measures submitted by Contractor and advise the ER accordingly; and

3. Review and advise the ET and ER on the effectiveness of the implemented mitigation measures.

1. Discuss with ET, IEC and Contractor on the implemented remedial measures;

2. Request Contractor to critically review the working methods;

3. Make agreement on the remedial measures to be implemented; and

4. Discuss with ET, IEC and Contractor on the effectiveness of the implemented remedial measures.

1. Identify source(s) of impact;

2. Inform the ER and confirm notification of the non-compliance in writing;

3. Rectify unacceptable practice;

4. Check all plant and equipment and consider changes of working methods;

5. Discuss with ET, IEC and ER and submit proposal of additional mitigation measures to ER and IEC within 3 working days of notification; and

6. Implement the agreed remedial measures.

Limit level exceedance for more than one consecutive sampling days

1. Inform IEC, contractor and ER;

2. Check monitoring data, all plant, equipment and Contractor¡¦s working methods;

3. Discuss mitigation measures with IEC, ER and Contractor; and

4. Ensure mitigation measures are implemented; and

5. Increase the monitoring frequency to daily until no exceedance of Limit Level for two consecutive days

1. Discuss with ET, Contractor and ER on the implemented mitigation measures;

2. Review the proposed remedial measures submitted by Contractor and advise the ER accordingly; and

3. Review and advise the ET and ER on the effectiveness of the implemented mitigation measures.

1. Discuss with ET, IEC and Contractor on the implemented remedial measures;

2. Request Contractor to critically review the working methods;

3. Make agreement on the remedial measures to be implemented;

4. Discuss with ET and IEC on the effectiveness of the implemented mitigation measures; and

5. Consider and instruct, if necessary, the Contractor to slow down or to stop all or part of the dredging activities until no exceedance of Limit level. 

1. Identify source(s) of impact;

2. Inform the ER and confirm notification of the non-compliance in writing;

3. Rectify unacceptable practice;

4. Check all plant and equipment and consider changes of working methods;

5. Discuss with ET, IEC and ER and submit proposal of additional mitigation measures to ER and IEC within 3 working days of notification; and

6. Implement the agreed remedial measures.

7. As directed by the ER, to slow down or stop all or part of the dredging activities until no exceedance of Limit level.

 

 


5                                          Landscape and Visual

5.1                                   Monitoring Requirement

According to the Updated EM&A Manual ([7]) of the Project, the landscape and visual baseline will be determined with reference to the habitat maps included in the EIA Report and detailed tree survey to be completed before the works can commence as well as preliminary site conditions verification surveys.  Given the majority of the Project area at TCE is marine water which will be reclaimed during the Project construction, limited number of trees will be affected by the Project and thus detailed tree survey was not undertaken as part of the landscape and visual baseline.  It is considered that site conditions verification surveys would be sufficient to represent the updated landscape and visual baseline for the Project.  The surveys were conducted in May 2018 to verify if there is any major change to the landscape and visual conditions with reference to the approved EIA Report.  Further details are presented in the following sections.

5.2                                   Monitoring Methodology

Site conditions verification surveys were conducted in May 2018 around the Project area.  In particular, the Landscape Resources (LRs) and Landscape Character Areas (LCAs) for the Project identified in the approved EIA Report (Figure 11.2a-al and Figure 11.3a-ac of the approved EIA Report) were revisited as far as practicable to verify if there is any major change of landscape baseline with reference to the approved EIA Report.

In addition, the visual sensitive receivers (VSRs) of the Project identified in the approved EIA Report (Figure 11.4a-aa of the approved EIA Report) were revisited as far as practicable to verify if there is any major change of visual baseline with reference to the approved EIA Report.

5.3                                   Monitoring Results

5.3.1                           Landscape Resources (LRs)

The identified LRs during the EIA stage include the followings and the detailed descriptions of the LRs were presented in the approved EIA Report:

Ÿ   LR1 ¡V Secondary Woodland

Ÿ   LR2 ¡V Shrubland and Grassland

Ÿ   LR3 ¡V Transitional Waters

Ÿ   LR4 ¡V Coastal Waters

Ÿ   LR5 ¡V Watercourses

Ÿ   LR6 ¡V Natural Shoreline

Ÿ   LR7 ¡V Roads, Urban Infrastructure and Major Transport Corridor

Ÿ   LR8 ¡V Village Type Development

Ÿ   LR9 ¡V Urbanised Area

Ÿ   LR10 ¡V Agricultural Land

Ÿ   LR11 ¡V Plantation

Ÿ   LR12 ¡V Mangroves

Ÿ   LR13 ¡V Fung Shui Woodland

Ÿ   LR14 ¡V Reedbed

Ÿ   LR15 ¡V Artificial Seawall

The site conditions verification surveys were conducted in May 2018 and these LRs were revisited as far as practicable ([8]).  The updated baseline conditions of the LRs are presented in Figure 5.1a-d.  During the site conditions verification surveys, no major change of landscape resource / element was identified.

5.3.2                           Landscape Character Areas (LCAs)

The identified LCAs during the EIA stage include the followings and the detailed descriptions of the LCAs were presented in the approved EIA Report:

LCA1 ¡V Inshore Water Landscape

LCA2 ¡V Strait Landscape

LCA3 ¡V Inter-tidal Coast Landscape

LCA4 ¡V Coastal Upland and Hillside Landscape

LCA5 ¡V Settled Valley Landscape

LCA6 ¡V Upland Hillside Landscape

LCA7 ¡V Reclamation / Ongoing Major Development Landscape 

LCA8 ¡V Transportation Corridor Landscape

LCA9 ¡V Mixed Modern Comprehensive Urban Development Landscape

LCA10 - Urban Peripheral Village and Rural Fringe Landscape

LCA11 ¡V Airport Landscape

LCA12 ¡V Institutional Landscape

LCA13¡VResidential Urban Landscape

The site conditions verification surveys were conducted in May 2018 and these LCAs were revisited as far as practicable ([9]).  The updated baseline conditions of the LCAs are presented in Figure 5.2a-b.  During the site conditions verification surveys, no major change of landscape character area / element was identified.

5.3.3                           Visual Sensitive Receivers (VSRs)

The updated views of the VSRs for the Project were taken from the same viewpoints, or nearby locations with similar views, as presented in the approved EIA Report on 15, 16, 17 and 19 May 2018.  Locations of these viewpoints are shown in Figure 5.3 ([10]).  The photographs showing the baseline condition as of August 2015 presented in the approved EIA Report and the updated baseline condition are presented in Figures 5.4a to 5.4u for comparison.

In general, the observed change of the baseline conditions when compared with those presented in the approved EIA Report are considered minor and do not significantly alter the overall landscape and visual baseline condition as illustrated in Figures 5.4a to 5.4u.  Therefore, the assessment results of the landscape and visual impact assessment as presented in the approved EIA Report is considered valid.  Additional landscape and visual mitigation measures other than those recommended in the approved EIA Report are thus not required.

The major differences between the baseline during the EIA stage and the updated baseline as observed in May 2018 are described below:

Southern Connection of Tuen Mun-Chek Lap Kok Link

During the EIA stage, it was assumed that the key construction elements (e.g. marine works) for the southern and northern connection of the Tuen Mun-Chek Lap Kok Link (TMCLKL) would be substantially completed by end of Year 2016.  The updated baseline in May 2018 showed that the majority of the viaduct section has been built, which is in line with the prediction as presented in the approved EIA Report.  As such, it does not affect the cumulative landscape and visual impact assessment results in the approved EIA Report. 

Hong Kong-Zhuhai Macao Bridge Hong Kong Boundary Crossing Facilities

During the EIA stage, it was assumed that the key construction elements for Hong Kong Boundary Crossing Facilities (HKBCF) would be substantially completed by end of Year 2016.  The updated baseline in May 2018 showed that the majority of the construction works for the HKBCF including the associated road transport network have been completed, which is in line with the prediction as presented in the approved EIA Report.  As such, it does not affect the cumulative landscape and visual impact assessment results in the approved EIA Report.

Planned Residential Developments in the Existing Tung Chung New Town

During the EIA stage, it was assumed that the residential developments at Tung Chung Area 55 and Area 56 near the Project would be completed in 2015-2016.  The updated baseline in May 2018 showed that these areas have been developed into private (Century Link and The Visionary) and public (Ying Tung Estate) housings respectively, which is in line with the prediction as presented in the approved EIA Report.  As such, it does not affect the cumulative landscape and visual impact assessment results in the approved EIA Report.

5.4                                   Summary

Base on the results of the site conditions verification surveys conducted in May 2018 with reference to the LRs and LCAs identified in the approved EIA Report, it is concluded that the landscape and visual baseline conditions within the Project site boundary is similar to those presented in the approved EIA Report.  The landscape and visual impact assessment in the approved EIA Report is thus considered valid.  There is no major change in the landscape and visual baseline conditions comparing to those during the EIA stage.  Additional landscape and visual mitigation measures other than those recommended in the approved EIA Report are thus not required.

6                                          Soft Shore Ecology

6.1                                   Monitoring Requirement

According to the Updated EM&A Manual ([11]) of the Project, baseline soft shore ecological monitoring shall be conducted once at each survey location of Tung Chung Bay (TCB) and Tai Ho Wan (THW) before reclamation. 

Further details of the baseline soft shore ecological monitoring conducted at TCB and THW under this Project are presented in the following sections.

6.2                                   Monitoring Locations

Baseline soft shore ecological monitoring was conducted at three (3) monitoring locations at TCB, situated in the eastern side (TCB1), southern side (TCB2) and western side (TCB3) as well as one (1) monitoring location at THW as shown in Figure 6.1.

6.3                                   Monitoring Methodology

The soft shore ecological monitoring consisted of qualitative walk-through surveys, quantitative transect surveys and sedimentation rate monitoring at the accessible survey locations of TCB and THW.

For qualitative walk-through surveys, the accessible shoreline of TCB and THW at each of the three shore heights: 2 m, 1.5 m and 1 m above Chart Datum was surveyed, and organisms encountered were recorded and their relative abundance noted.  In particular, active search of horseshoe crabs and seagrasses were conducted to confirm whether these species are present along the sites. 

For quantitative transect survey, one 50 ¡V 100 m horizontal (belt) transect (actual length subject to the site conditions) was surveyed at each of the three shore heights: 2 m, 1.5 m and 1 m above Chart Datum of each survey location.  On each transect, five quadrats (50 cm x 50 cm) were placed randomly in each transect to assess the abundance and distribution of flora and fauna.  For each quadrat, surface layer to 5 cm depth was sieved and microbenthic organisms (e.g. crustaceans) were recorded and identified.  Density of organisms was expressed as individuals / m2.  Areas with seagrass were also recorded and identified and other information, such as the percentage cover, were also recorded.  Sessile animals such as barnacles and oysters in each quadrat were not counted but estimated as percentage cover on the rock surface.  All species of algae (encrusting, foliose and filamentous) were also identified and recorded by estimating the percentage cover on the rock surface.  All organisms were identified to the lowest possible taxonomic level (at least Genus level).  Species encountered outside the quadrat but in the vicinity of survey transect were also recorded.

For sedimentation rate monitoring, to avoid disturbance to the mudflat and nuisance to navigation, no fixed marker/monitoring rod was installed at the monitoring stations.  A high precision Global Navigation Satellite System (GNSS) real time location fixing system (or equivalent technology) was used to locate the station in the precision of 1 mm, which is reasonable under flat mudflat topography with uneven mudflat surface only at micro level.   

Measurements were taken directly on the mudflat surface.  The Real Time Kinematic GNSS (RTK GNSS) surveying technology was used to measure mudflat surface levels and 3D coordinates of a survey point.  The RTK GNSS survey was calibrated against a reference station in the field before and after each survey.  The reference station is a survey control point established by the Lands Department of the HKSAR Government or traditional land surveying methods using professional surveying instruments such as total station, level and/or geodetic global navigation satellite system.  The coordinates system is in HK1980 GRID system.  The reference control station was surveyed and established by traditional land surveying methods using professional surveying instruments such as total station, level and/or geodetic GNSS.  The accuracy was down to mm level and higher than the proposed RTK GNSS cm level so that the reference control station has relatively higher accuracy.  As the reference control station has higher accuracy, it was set as true evaluation relative to the RTK GNSS measurement.  All position and height correction were adjusted and corrected to the reference control station. 

The precision of the measured mudflat surface level reading (vertical precision setting) was within 10 mm (standard deviation) after averaging the valid survey records of the XYZ HK1980 GRID coordinates.  Each survey record at each station was computed by averaging at least three measurements that are within the above specified precision setting.  Both digital data logging and written records were collected in the field.  Field data on station fixing and mudflat surface measurement were recorded.

6.4                                   Baseline Monitoring Results

6.4.1                           General

The soft shore ecological monitoring was conducted in April to June 2018 as presented in Table 6.1 below.  Representative photographs taken during the baseline monitoring are presented in Figure 6.2.

Table 6.1        Date and Activities of Baseline Soft Shore Ecological Monitoring

Date

Time

Activity

30 April 2018

12:00 - 17:30

Quantitative transect survey at TCB3

2 May 2018

12:30 ¡V 18:00

Quantitative transect survey at TCB1

3 May 2018

13:30 ¡V 18:00

Qualitative walk-through survey and quantitative transect survey at TCB2

4 May 2018

15:30 ¡V 18:00

Quantitative transect survey at TCB3

16 May 2018

14:00 ¡V 17:00

Qualitative walk-through survey at TCB3 and sedimentation rate monitoring at TCB1, TCB2 and TCB3

17 May 2018

14:30 ¡V 17:00

Qualitative walk-through survey and quantitative transect survey at TCB1

27 June 2018

11:30 ¡V 16:30

Qualitative walk-through survey, quantitative transect survey and sedimentation rate monitoring at THW

6.4.2                           Qualitative Walk-through Surveys

Horseshoe Crabs

The results for horseshoe crabs during qualitative walk-through surveys are presented in Table 6.2 below.  A total of 13, 11 and 9 individuals of Tachypleus tridentatus were recorded at TCB1, TCB3 and THW, respectively.  A total of 4 individuals of Carcinoscorpius rotundicauda were recorded at THW.  The mean prosomal widths of the observed horseshoe crab individuals were 4.8 cm, 6.0 cm and 3.4 cm at TCB1, TCB3 and THW, respectively.  Horseshoe crab was not observed at TCB2.

Table 6.2        Results for Horseshoe Crabs during Qualitative Walk-through Surveys

Sighting #

Species

Prosomal Width (cm)

Total Length (cm)

Monitoring Date: 17 May 2018 15:00-17:00

Monitoring Station: TCB1

1

Tachypleus tridentatus

4.2

7.3

2

Tachypleus tridentatus

3.9

7.6

3

Tachypleus tridentatus

1.4

1.8

4

Tachypleus tridentatus

4.9

9.1

5

Tachypleus tridentatus

3.9

8.7

6

Tachypleus tridentatus

5.0

9.5

7

Tachypleus tridentatus

4.6

9.7

8

Tachypleus tridentatus

3.8

8.0

9

Tachypleus tridentatus

3.4

6.8

10

Tachypleus tridentatus

3.1

5.2

11

Tachypleus tridentatus

4.8

9.9

12

Tachypleus tridentatus

4.7

9.0

13

Tachypleus tridentatus

14.1

30.0

 

Mean (Range)

4.8 (1.4-14.1)

9.4 (1.8-30.0)

 

 

 

 

 

 

 

 

 

 

 

 

Monitoring Date: 16 May 2018 14:30-16:30

Monitoring Station: TCB3

1

Tachypleus tridentatus

13.5

28.0

2

Tachypleus tridentatus

5.0

9.9

3

Tachypleus tridentatus

4.1

8.9

4

Tachypleus tridentatus

5.6

11.7

5

Tachypleus tridentatus

6.5

12.1

6

Tachypleus tridentatus

4.2

8.4

7

Tachypleus tridentatus

6.4

13.4

8

Tachypleus tridentatus

4.7

9.9

9

Tachypleus tridentatus

4.3

8.4

10

Tachypleus tridentatus

6.4

14.3

11

Tachypleus tridentatus

5.4

10.6

 

Mean (Range)

6.0 (4.1-13.5)

12.3 (8.4-28.0)

 

 

 

 

Monitoring Date: 27 June 2018 12:30-16:30

Monitoring Station: THW

1

Tachypleus tridentatus

2.2

3.8

2

Tachypleus tridentatus

2.1

3.3

3

Tachypleus tridentatus

2.8

5.5

4

Tachypleus tridentatus

2.7

4.1

5

Carcinoscorpius rotundicauda

3.6

7.6

6

Tachypleus tridentatus

3.3

5.6

7

Carcinoscorpius rotundicauda

2.5

5.0

8

Carcinoscorpius rotundicauda

3.8

7.8

9

Tachypleus tridentatus

3.5

3.0

10

Tachypleus tridentatus

3.6

6.0

11

Tachypleus tridentatus

4.2

6.8

12

Carcinoscorpius rotundicauda

4.5

8.0

13

Tachypleus tridentatus

5.2

7.5

 

Mean (Range)

3.4 (2.1-5.2)

5.7 (3.0-8.0)

Seagrass Beds

Seagrass beds were not observed during the qualitative walk-through surveys at TCB1, TCB2, TCB3 and THW.

Other Intertidal Soft Shore Communities

The survey results on other intertidal soft shore communities are summarised in Table 6.3 below.  A total of 35, 29, 38 and 40 species were recorded during the qualitative walk-through surveys at TCB1, TCB2, TCB3 and THW, respectively.  Detailed species list and their relative abundance at each monitoring station are presented in Annex D1. 

Table 6.3        Results for Other Intertidal Soft Shore Communities during Qualitative Walk-through Surveys

Monitoring Station

Shore Height *

No. of Species

TCB1

H

21

 

M

27

 

L

25

 

Overall

35

 

 

 

TCB2

H

21

 

M

22

 

L

25

 

Overall

29

 

 

 

TCB3

H

15

 

M

26

 

L

26

 

Overall

38

 

 

 

THW

H

25

 

M

28

 

L

30

 

Overall

40

* H: +2mCD; M: +1.5mCD; L: +1mCD

6.4.3                           Quantitative Transect Surveys

A total of 8,043 individuals were recorded from all transects at monitoring stations TCB1-3 and THW.  The most abundant group of intertidal soft shore communities recorded was gastropods, with a total of 7,768 individuals (relative abundance of 96.6% and density of 518 individual m-2).  The summary of the top three dominant species at each shore height of each monitoring station is presented in Table 6.4.  The complete list of species and density recorded is shown in Annex E2.

Table 6.4        Results for Other Intertidal Soft Shore Communities during Quantitative Transect Surveys

Monitoring Station

Shore Height *

Top Three Dominant Species

Density
(ind. / m2)

TCB1

H

1

Batillaria multiformis

1216.0

 

 

2

Monodonta labio

24.8

 

 

3

Clithon spp.

12.0

 

M

1

Cerithidea cingulata

197.6

 

 

2

Batillaria multiformis

181.6

 

 

3

Monodonta labio

58.4

 

L

1

Batillaria multiformis

95.2

 

 

2

Batillaria zonalis

50.4

 

 

3

Nipponacmea concinna

39.2

 

 

 

 

 

TCB2

H

1

Batillaria multiformis

4.0

 

 

2

Laternula anatina

3.2

 

 

3

Batillaria zonalis

3.2

 

M

1

Batillaria multiformis

131.2

 

 

2

Cerithidea cingulata

36.8

 

 

3

Cellana grata

33.6

 

L

1

Batillaria multiformis

300.0

 

 

2

Batillaria zonalis

39.2

 

 

3

Cerithidea cingulata

36.8

 

 

 

 

 

TCB3

H

1

Batillaria multiformis

1,780.0

 

 

2

Batillaria zonalis

60.0

 

 

3

Littoraria articulata

19.2

 

M

1

Batillaria multiformis

741.6

 

 

2

Cellana grata

40.0

 

 

3

Monodonta labio

40.0

 

L

1

Batillaria multiformis

112.8

 

 

2

Monodonta labio

22.4

 

 

3

Lunella coronata

19.2

 

 

 

 

 

THW

H

1

Cerithidea diadjariensis

108.8

 

 

2

Batillaria zonalis

44.0

 

 

3

Geloina erosa

42.4

 

M

1

Cerithidea diadjariensis

127.2

 

 

2

Batillaria zonalis

73.6

 

 

3

Cerithidea cingulata

47.2

 

L

1

Batillaria zonalis

91.2

 

 

2

Cerithidea diadjariensis

72.8

 

 

3

Cerithidea cingulata

40.0

* H: +2mCD; M: +1.5mCD; L: +1mCD

6.4.4                           Sedimentation Rate Monitoring

The mudflat surface levels at the four selected monitoring stations and the corresponding XYZ HK1980 GRID coordinates are presented in Table 6.5.

Table 6.5        Results of Sedimentation Rate Monitoring

Monitoring Station

Northing (m)

Easting (m)

Z level (Initial Sedimentation Rate) (mPD)

Remarks

TCB1

816068.626

811129.309

1.252

Soft mudflat

TCB2

815812.382

810917.245

1.120

Soft mudflat

TCB3

816027.632

810696.839

1.041

Soft mudflat

THW

817472.067

815850.407

1.016

Soft mudflat

6.5                                   Event and Action Plan

In the event of the impact monitoring results indicating that the density or the distribution pattern of horseshoe crab, seagrass and intertidal soft shore communities is found to be significant different to the baseline condition (taking into account natural fluctuation in the occurrence and distribution pattern such as due to seasonal change), appropriate actions should be taken and additional mitigation measures should be implemented as necessary after agreement with IEC and ER.  Data should also be re-assessed to determine the need for any further monitoring.  The event and action plan, as proposed in Table 6.6, should be undertaken within a period of 1 month after a significant difference has been determined.


Table 6.6        Event and Action Plan for Soft Shore Ecological Monitoring

Event

Action

ET

IEC

ER

Contractor

Density or the distribution pattern of horseshoe crab, seagrass and intertidal soft shore communities recorded in the impact or post-construction monitoring are  significantly lower than or different from those recorded in the baseline monitoring.

1. Review historical data to ensure differences are as a result of natural variation or previously observed seasonal differences;

2. Identify source(s) of impact;

3. Inform the IEC, ER and Contractor;

4. Check monitoring data;

5. Discuss additional monitoring and any other measures, with the IEC, ER and Contractor.

1. Discuss amongst ER, ET, and Contractor on the potential remedial actions;

2. Review proposals for additional monitoring and any other measures submitted by the Contractor and advise the ER accordingly;

3. Supervise the implementation of remedial measures.

1. Discuss with the IEC additional monitoring requirements and any other measures proposed by the ET;

2. Make agreement on the measures to be implemented.

 

1. Inform the ER and in writing;

2. Discuss with the ET and the IEC and propose measures to the IEC and the ER;

3. Implement the agreed measures;

4. Resubmit proposals of remedial actions if problem still not under control;

5. Stop the relevant portion of works as determined by the ER until the exceedance is abated.

 


7                                          Conclusion

In accordance with the Updated EM&A Manual of the Project, baseline monitoring was undertaken prior to commencement of the construction works for the following baseline monitoring components:

Ÿ   Air Quality;

Ÿ   Noise;

Ÿ   Water Quality;

Ÿ   Landscape and Visual; and

Ÿ   Soft Shore Ecology.

The baseline air quality monitoring was conducted at four (4) monitoring stations (DM-1, DM-2A, DM-3A and DM-4A) between 4 and 17 May 2018.  Overall, the baseline air quality monitoring results are considered representative to the ambient air quality conditions of the sensitive receivers in the vicinity of the Project.  The Action and Limit Levels for air quality (1-hour TSP levels) were established based on the baseline monitoring results.

 

Baseline noise monitoring was conducted at four (4) monitoring stations (NMS-CA-1A, NMS-CA-2A, NMS-CA-3 and NMS-CA-4) between 4 and 18 May 2018.  The major noise sources identified at the monitoring station are the noise from road traffic, aircraft, train, renovation at Ying Tung Estate and insect.  The baseline monitoring results are considered representative of the ambient noise level.

Baseline water quality monitoring was conducted at seven (7) monitoring stations (TCE-C1, TCE-C2, TCE-WQM1, TCE-WQM2a, TCE-WQM2b, TCE-WQM3A and TCE-WQM4) between 25 April and 21 May 2018.  No observable pollution source was recorded at the monitoring stations and the baseline monitoring results are thus considered representative of the ambient water quality levels.  Action and Limit Levels were established for DO, SS and Turbidity based on the baseline monitoring results.

 

Site conditions verification surveys for landscape and visual baseline were conducted on 15, 16, 17 and 19 May 2018 to revisit the identified LRs, LCAs and VSRs in the approved EIA Report.  The survey results concluded that the landscape and visual baseline conditions within the Project site boundary is similar to those presented in the approved EIA Report.  There is no major change in the landscape and visual baseline conditions comparing to those during the EIA stage.  Additional landscape and visual mitigation measures other than those recommended in the approved EIA Report are thus not required.

 

Baseline soft shore ecological monitoring was conducted at four (4) monitoring stations situated in TCB and THW on 30 April, 2-4 May, 15-16 May and 27 June 2018.  A total of 8,043 intertidal individuals and 37 individuals of horseshoe crabs were recorded during the surveys.  The baseline mudflat surface levels at the four (4) monitoring stations were also measured for the determination of sedimentation rate during the impact/post-construction monitoring.  Event and Action Plan is established for implementing appropriate actions and additional mitigation measures as necessary when comparing the data between baseline and impact/post-construction monitoring.


 



([1])        Arup (2015).  Environmental Impact Assessment Report for Tung Chung New Town Extension. Deposited to EPD under Register No. AEIAR-196/2016

([2])        ERM (2018).  Environmental Monitoring and Audit Manual for Tung Chung New Town Extension. Deposited to EPD under EP-519/2016

([3])        Arup (2015).  Op cit.

([4])        ERM (2018). Op cit.

([5])        ERM (2018). Op cit.

([6])        ERM (2018). Op cit.

([7])        ERM (2018). Op cit.

([8])        LR12 (Fung Shui Woodland) was not revisited during the site conditions verification surveys as it is relevant to TCW, which will be verified separately prior to the construction of TCW.

([9])        LCA5 (Settled Valley Landscape), LCA6 (Upland and Hillside Landscape), LCA11 (Airport Landscape) and LCA12 (Institutional Landscape) were not revisited during the site conditions verification surveys as it is relevant to TCW, which will be verified separately prior to the construction of TCW.

([10])      VSR6-11, VSR13-17, VSR19, VSR21-25, VSR30-32, VSR34, VSR38-39 and VSR44 were not revisited during the site conditions verification surveys as it is relevant to TCW, which will be verified separately prior to the construction of TCW.

([11])      ERM (2018). Op cit.